: In April 2026 , Vizsla awarded an EPCM contract to M3 Engineering and a mine design contract to Mining Plus .
Vizsla Silver reached several critical milestones for its flagship in late 2024 and 2025, transitioning the asset from advanced exploration toward construction readiness. Key Project Milestones (2024–2025) Vizsla Silver guides for a September Panuco pro...
: The company anticipates receiving the MIA environmental permit in mid-2026, which is required to make a formal construction decision. : In April 2026 , Vizsla awarded an
: Initial silver production is currently targeted for the second half of 2027 . Expert Perspectives : Initial silver production is currently targeted for
: The project is considered fully funded , supported by over US$450 million in cash and a US$300 million convertible senior notes offering closed in late 2025.
: Released in July 2024 , this study established a robust economic foundation, projecting 15.2 million ounces of annual silver equivalent (AgEq) production and a 9-month payback period.